Easy Peasy Software Logo

Using The Project Summary Window

The Project Summary Window is the first window you see when you open a Project Database.

It's not hard to tell that its main purpose is as a "Dashboard Window" for the project you're working with.

Its secondary purpose is to give you a set of hyperlinks for creating database records, or locating, and displaying records.

A Project Record

Understanding What The Task Completion Rate Panel Is Telling You

The first two panels in the center of the window are easy to understand, so I'm not going to explain them, but the Task Completion Rate Panel, shown in the image below needs some explaining.

Task Completion Rate Panel

The panel's Task Completion Rate line shows you the rate (in percent) that all of the project's finished work is currently being completed at.

Task Completion Rate Panel

Knowing this rate, helps you get closer to a true estimate for how much longer some unfinished task will take, assuming of course that nothing, or very little goes wrong during the work sessions.

If you create a new Task record and you estimate that it will take 1 hour to finish that task. But, you're working at a completion rate of 60.98% of a Task's estimated completion time, then if nothing goes wrong, you'll probably finish that task in 36 to 37 minutes, instead of the estimated 60 minutes. The calculation is shown below.

Task Record's Estimated Completion Time = 60 min
Project's Current Task Completion Rate = 60.98% = 0.6098
60 min * 0.6098 = 36.588 min = 37 minutes (approx).

One of the most important things to understand about estimates, is that they are just guesses about what will happen in the future. They are not, realities!

The Estimated Time To Complete All Unfinished Tasks section of the panel is something that can be confusing to people too.

Table of estimated times to complete all unfinished tasks, when things are going wrong.

This panel is looking at the estimated completion time for all of the project's unfinished tasks, and the current task completion rate.

Then it uses these two values to estimate how long it would take to actually complete these unfinished tasks under the following conditions.

Table of estimated times to complete all unfinished tasks, when things are going wrong.

The Delay Factor value in each of the table's lines, is a percentage of things going wrong during all of the work sessions needed to finish all the project's unfinished tasks.

0% delay is a perfect case. 50% delay is a total nightmare scenario. Somewhere between 0% and 30% of things going wrong in a work session and delaying the task's completion time is where most work sessions tend to end up at.

When people ask me how long do I think something is going to take to complete, I like to look at this table, and quote estimate values based on what I'm seeing in the 30% and 50% rows in that table.

I do that because, while I strive to work, and plan things, in a state of perfection at all times, reality never lets me do that for very long. Somewhere along the line, my fault or not, something is going to go wrong, and then my estimated completion time, is probably not going to end up being my actual completion time.

When this happens, the one certainty that I always have, is that my "Work My Butt Off" rate, is about to rise sharply.